| | MANAGER'S REPORT:
This bid award is for material procurement for the downtown waterfront improvements project at the Archipelago property. The materials sought are long lead-time items; procuring them now will assure that the desired construction schedule is met.
Bids were opened on this project on January 15, 2019. Results of the bid opening were as follows:
Bidders |
Total Bid |
Island Contractors |
$783,820 |
Trucano Construction |
$849,017 |
Western Marine Construction |
$840,600 |
Engineer's Estimate |
$833,000 |
| |