MANAGER'S REPORT:
Bartlett Hospital wishes to add a third floor to the Behavioral Health Facility Project. The project bid was awarded in March for approximately $8.5M for the demolition of an old building and the construction of a new two-story facility.
The addition of a third floor would require a Supplemental Agreement as governed by CBJ’s purchasing code and the dollar amount of the approval requires Assembly approval, provided that the Manager provides a best interest finding. That finding is in the Assembly packet.
The City Manager recommends that the Assembly accept the best interest finding and authorize the execution of Supplemental Agreements to the Behavioral Health facility construction contract with Dawson Construction Company to facilitate the addition of a third floor to the new facility.
|