Bid E14-022 Pioneer Avenue Reconstruction Phase III

MANAGER'S REPORT:

This project consists of reconstruction of Pioneer Avenue from No. 3151 Pioneer Avenue through the Blueberry Hills Road intersection.

Bids for this project were opened on November 8, 2013. The bid protest period expired at 4:30 p.m. on November 13, 2013. Results of the bid opening are as follows:  

Responsive Bidders                           Total Bid
Arete Construction Corp.                    $1,034,925.00
Admiralty Construction Inc.               $1,047,885.00

Engineer's Estimate:  $1,043,044.00

I recommend Award of this project to Arete Construction, Corp. for the total amount bid of $1,034,925.00.